Tucketts Clyce, Somerset

For Kier

2019

As part of Somerset’s flood defences, TMS were called in to replace a failing outfall head wall along the bank
of the estuary at Tuckett’s Clyce in Somerset. Using 16m steel sheet piles, TMS constructed a new cofferdam
head wall directly in front of the original head wall, therefore allowing safe demolition of the failing
structure. In addition to the sheet piles, additional anchor piles were installed and attached with steel tie
bars to ensure no movement could occur.

View Project

Teignmouth Fish Quay

For Interserve

November 2015

TMS were engaged by Interserve to commence
works in November 15 to demolish the existing
timber fish quay and construct a replacement steel
sheet piled marine structure on the popular Back
Beach area of Teignmouth, Devon. The location
of the site meant that the works took place in
very close proximity to residential properties and
beach users. Construction methods, working
hours and selection of plant was therefore of
critical importance so as not to adversely disturb
neighbours to the site and affect the peaceful
enjoyment of the beach by the local community
and tourists.

View Project

Stonehaven Pier Reconstruction

For Aberdeenshire Council

May 2022 - October 2022

Working on behalf of Aberdeenshire
Council, TMS were appointed as Principal Contractor
to construct three new pier heads around three
historic ones in Stonehaven Harbour. The three new
pier heads were to encapsulate the existing Net Pier,
South Pier and Fish Jetty structures which had all
been considered to have reached the end of their
serviceable life and were at risk of failure if their
condition were allowed to degrade further. The full
scope of the project included:

View Project

Toft Pier Redevelopment

For Shetland Isles Council

18 Months

Working on behalf of Shetland Islands Council, TMS were appointed as Principal Contractor for the construction of a new pier in Toft
at the north end of Shetland Mainland. The work was completed over an 18-month period with a break during the winter ‘windy’
season and a further break forced by the recent COVID-19 construction shut-down. TMS worked closely with Shetland Island Council
to develop ‘COVID Safe’ practices to allow safe and timely return to the island for continuation of the works during the on-going
pandemic. The new pier was required to replace a redundant, much smaller jetty that had once served as the inter-island ferry berth.
Following relocation of the ferry to a new “roll on/roll off” berth, the original jetty had fallen into disrepair and TMS were therefore
Tappointed to construct a new pier to be used for the operation of the islands’ fish-farming vessels.

View Project

Pontoon Piles, Newhaven

For Rampion Offshore Windfarm

5 Months

Working on behalf of Knights Brown, TMS were appointed to complete the marine works for the installation of new
pontoons at Rampion Offshore Wind Farm’s landing facility in the Port of Newhaven. TMS completed the piling works from marine
floating plant with a 135t crawler crane and 60t long-reach mobilised on the barge deck. The piles were installed using a PVE 25M
standard frequency vibro hammer. All of the new pontoons were successfully configured on the new piles as all of the piles were
positioned within small tolerance

View Project

Newquay North Quay Refurb

For Cornwall County Council

24 Weeks

TMS Maritime were awarded the Design and Build contract for the restoration and refurbishment works to Newquay Harbour’s North Pier.
The historic North Pier is constructed of mortared granite masonry, built in the mid 19th century and is Grade 2 listed. The Pier extends from
North Quay Road approximately 70m out into Newquay Harbour. The Quay / Pier is 16m wide and the Pier height increases from 6.5m to
9.9m above adjacent beach level.

View Project