Littlehampton West Training Wall Replacement

For Littlehampton Harbour Board

9 Weeks

The unusually narrow harbour entrance at Littlehampton drains a catchment of 966km2 including the Arun’s main tributary, the Rother. The entrance to the harbour is protected from
siltation through the presence of river training walls and piers at the mouth of the river, including the west training wall.

View Project

Stonehaven Pier Reconstruction

For Aberdeenshire Council

May 2022 - October 2022

Working on behalf of Aberdeenshire
Council, TMS were appointed as Principal Contractor
to construct three new pier heads around three
historic ones in Stonehaven Harbour. The three new
pier heads were to encapsulate the existing Net Pier,
South Pier and Fish Jetty structures which had all
been considered to have reached the end of their
serviceable life and were at risk of failure if their
condition were allowed to degrade further. The full
scope of the project included:

View Project

Toft Pier Redevelopment

For Shetland Isles Council

18 Months

Working on behalf of Shetland Islands Council, TMS were appointed as Principal Contractor for the construction of a new pier in Toft
at the north end of Shetland Mainland. The work was completed over an 18-month period with a break during the winter ‘windy’
season and a further break forced by the recent COVID-19 construction shut-down. TMS worked closely with Shetland Island Council
to develop ‘COVID Safe’ practices to allow safe and timely return to the island for continuation of the works during the on-going
pandemic. The new pier was required to replace a redundant, much smaller jetty that had once served as the inter-island ferry berth.
Following relocation of the ferry to a new “roll on/roll off” berth, the original jetty had fallen into disrepair and TMS were therefore
Tappointed to construct a new pier to be used for the operation of the islands’ fish-farming vessels.

View Project

Pontoon Piles, Newhaven

For Rampion Offshore Windfarm

5 Months

Working on behalf of Knights Brown, TMS were appointed to complete the marine works for the installation of new
pontoons at Rampion Offshore Wind Farm’s landing facility in the Port of Newhaven. TMS completed the piling works from marine
floating plant with a 135t crawler crane and 60t long-reach mobilised on the barge deck. The piles were installed using a PVE 25M
standard frequency vibro hammer. All of the new pontoons were successfully configured on the new piles as all of the piles were
positioned within small tolerance

View Project