Teignmouth – Sea Wall reinforcing

TMS are still hard at work in Teignmouth replacing and reinforcing the toe of the sea wall, here are some pictures showing works carried out over the last couple of weeks.

We have started to pour the capping beam for the piles and are continuing to do so within the tidal window TMS have been reducing the beach level with a dozer to enable the start of the ground anchoring to support the piles on the higher side. We are also installing anchor guides behind the new pile line to enable the grouting of the new ties

Teignmout Point