TMS CUSTOMER SATISFACTION TESTIMONIALS

TMS continue to complete high quality complex marine contracts gaining positive feedback from their clients. The following testimonials are extracts from customer satisfaction surveys on recently completed projects

Tonbridge Castle River Repair and Stabilisation – Tonbridge & Malling Borough Council

Work was completed ahead of programme… All staff were very responsive and easy to communicate with.  The fact the company was based in Devon was never an issue, staff were willing to travel long distances for relatively short meetings. A very professional and reliable company.”

Stuart Edwards – Property Services Officer Tonbridge & Malling Borough Council

“TMS completed the project ahead of the contract programme despite additional works being added, whilst maintaining a high standard of work and professional approach… The service could not be faulted. I am not aware of anything that could have been improved upon. We were kept informed of items as the project progressed and responses were received in a very timely fashion.”

Peter Thorpe Associate Director Betteridge & Milson

 

Salmons Brook River Bank Stabilisation – London Waste Limited

“The job was completed earlier than scheduled, despite the unexpected constraints during construction….. In general we are satisfied with the cooperation between teams on site and at the office.”

Amec Foster Wheeler, Endorsed by London Waste Limited

TMS Complete Historic River Wall Repair

TMS have just completed the river wall repair at the historic Tonbridge Castle.

Tonbridge Marine river wall repair

Using  in house marine plant and directly employed staff, TMS have completed another successful marine contract.

TMS Site Manager Roy Francis commented “It has been a lovely location to work, carrying out the repairs with the castle in the background has made it a nice place to be”